PRJ-10 · Tilden Mine

Concentrator Desliming & Recovery Optimization

Project PRJ-10: Process Chemistry Optimization — Concentrator
Site Tilden Mine — Concentrator (desliming + flotation circuits)
Champions Keith Holmgren (Sr. Dir. Mining Tech), Sean Halston (Concentrator Ops)
Key SMEs Ryan Korpela (Site Leader), Met tech team
Vooban Lead Pascal Lalancette
IE Lead Erico Lemos (PM), Bob Zadel (Sr. Technical Advisor)
Duration Phase 1: 7 weeks · Phase 2: 12 weeks (17–19 total)
Status Phase 1 Active

Charter Snapshot

A 17–19 week POV deploying four integrated AI components around the desliming circuit. Phase 1 proves the core thesis with a hard go/no-go gate at Week 7. Phase 2 builds the full system.

Four-Component AI Stack

Component ID Role
Desliming Optimization Model TLD-23 Core — dispersant dosing guidance per section
Flotation Recovery Feedback Loop TLD-08 Outcome validation — measures downstream impact
Live CRP / Operator Decision Support TLD-32 Delivery surface — how met techs use all of this
Beaker Test Vision TLD-54 Measurement enabler — replaces subjective visual assessment

Scope Boundaries

In scope: Desliming circuit (all 4 milling sections), flotation as outcome measurement, beaker vision pilot, live operator advisory dashboard

Explicitly out: Grinding optimization (Keith excluded), mine-to-concentrator ore tracking (deferred to TLD-P17), water chemistry as control variable, automated DCS write-back


Progress

Phase 1: Proof of Value (Weeks 0–7)

Phase Weeks Status Key Activities
Data Readiness Confirmation 0 Not started PAA data availability, D-slime grab sample export, Pi tag list, coordinator confirmed
Data Ingestion & Baseline 1–2 Not started Ingest Pi/DCS/met balance, establish weight recovery baseline per section, variability analysis
Desliming Model & Flotation Correlation 3–5 Not started Feature engineering, hybrid model (rules + ML), backtest on historical data, flotation correlation
Mid-Point Review 6 Not started Preliminary results with Ryan, Keith, operations stakeholders
Hard Gate — Phase 1 Deliverables 7 Not started Go/no-go decision on Phase 2

Phase 2: Full System Build (Weeks 8–19)

Phase Weeks Status Key Activities
Team Ramp & Beaker Vision 8–10 Future Full team ramp, camera deployment at PSI stations, live CRP prototype
System Integration & Operator Training 11–15 Future Live advisory dashboard, flotation feedback loop, met tech workflow integration
Measured Improvement & Handoff 16–19 Future Recovery improvement measurement, operational handoff, sustainability plan

Key Metrics

Metric Baseline Target Current
Weight recovery 36–42% (variable) Reduce variability, shift upward
Section-to-section variability High (unquantified) Quantified, then reduced
Operator-to-operator variability High (subjective beaker tests) Standardized via beaker vision
Flotation stability Periodic flooding events Predictable, preventable
Dispersant dosing consistency Manual, experience-dependent Model-guided, per-section

Value anchor: Each 1% weight recovery improvement = ~100,000 additional tons = tens of millions $/yr. $50M/yr reagent spend as optimization surface.


Decisions Log

# Decision Owner Deadline Status
1 PAA dispersant data: DCS/Pi logged vs. paper-only? Keith Holmgren Week 0 Pending
2 Day-to-day coordinator appointment Ryan Korpela Week 0 Pending
3 IT/OT data access pre-approval CLF IT Week 0 Pending
4 Phase 2 go/no-go Ryan Korpela / Chad Asgaard Week 7 Future
5 Beaker vision PSI station selection (1–2 stations) Keith Holmgren Week 8 Future

CLF Accountability

What Cleveland-Cliffs owns. These items gate project progress — delays here delay delivery.

CLF Deliverables

# Deliverable Owner Phase Status
CLF1 Data access provisioning — Pi historian, DCS, met balance exports CLF IT/OT Pre-kickoff + Phase 1 Pending
CLF2 SME time commitment — Keith Holmgren + backup SMEs Keith Holmgren Phase 1 + 2 Pending
CLF3 Met tech participation — 2–3 reps for workflow mapping + validation Concentrator Ops Phase 2 Future
CLF4 Pilot PSI station access — beaker vision camera installation Keith Holmgren Phase 2 (Week 8) Future
CLF5 Day-to-day champion assignment Ryan Korpela Pre-kickoff Pending
CLF6 Decision gate participation — Week 7 + Week 19 Ryan + Chad Phase 1 + 2 Future

Pre-Kickoff Data (Week 0)

# Item Owner Status
A1 D-slime grab sample spreadsheet Concentrator Ops Pending
A2 Metallurgical balance records (12+ months) Concentrator Ops Pending
B1 PAA dispersant logging confirmation (DCS/Pi vs. paper) Keith Holmgren Pending
C6 Pi historian tag list for desliming + flotation circuits CLF IT/OT Pending
D1 Day-to-day coordinator confirmed Ryan Korpela Pending

Week 1 Data Ingestion

Source Data Owner Status
Pi historian Dispersant rates, tailing sump levels, DTU pump speeds, thickener profiles, flotation params (12+ months) CLF IT/OT Not started
DCS (Foxboro) Control setpoints, process measurements, met tech dispersant inputs CLF IT/OT Not started
Silica analyzer Flotation circuit readings (7-min intervals) Concentrator Ops Not started
Reagent records Dispersant + amine consumption by type, dosing rates, cost data Concentrator Ops Not started

Named CLF Roles

Role Person Accountability
Site sponsor Ryan Korpela Go/no-go decisions, executive escalation
Corporate sponsor Chad Asgaard Phase gate decisions, resource authorization
Sr. Dir. Mining Technology Keith Holmgren Process framework, SME knowledge, scope decisions
Concentrator Ops Sean Halston Day-to-day operations context, met tech coordination
Day-to-day coordinator TBD Data logistics, scheduling, first point of contact

Two pre-kickoff items outstanding

Day-to-day coordinator not yet assigned. PAA dispersant logging not yet confirmed as DCS/Pi-logged vs. paper-only — this determines the entire modeling approach.


Blockers

# Blocker Since Owner Impact
No active blockers

Activity Feed

Date Update
Apr 7 IE x Tilden scoping call: scope locked to desliming + flotation recovery. Grinding excluded by Keith. Charter v2 submitted.
Mar 24 Chad Asgaard directed concentrator focus at corporate readout. "Make money, not life easier."
Mar 14 Tilden readout — Ryan: "really impressed." All 4 projects validated. Concentrator = #1 priority.

Governance

Touchpoint Timing Audience
Weekly status Every Friday Project team (Vooban + IE + CLF coordinator)
Week 2 checkpoint End of Week 2 Data reality check — Keith + Vooban
Week 6 mid-point review Mid-Phase 1 Ryan, Keith, operations stakeholders
Week 7 hard gate End of Phase 1 Go/no-go: Ryan + Chad
Week 14 system review Mid-Phase 2 Full leadership review
Week 19 final demo End of POV Site + corporate leadership